Yajva Combined Cycle Natural Gas Power Plant
Perm Territory · Russian Federation
Founder of our company and Resul Zeyrekçi, Chairman of the Board of Directors, served as a senior manager in many projects abroad and assumed important responsibilities in the successful completion and delivery of these projects.
ENR 2013 Global Best Project Award
The project was awarded the first prize in the Energy and Industrial category in the "Global Best Projects 2013" competition of Engineering News-Record (ENR) magazine.
About the Project
ENKA was selected by the employer E.ON Russia to undertake the engineering, procurement and construction (EPC) works of the Yajva Combined Cycle Power Plant. The project includes the single-shaft Siemens 1×SCC5-4000F-1S power unit and all its support facilities.
Main Power Unit
- ✓Siemens SGT5-4000F gas turbine
- ✓Steam turbine
- ✓Generator
- ✓Condenser
- ✓CMI production vertical natural circulation waste heat boiler (HRSG)
Support Facilities
Project Highlights
- ▸Built in full compliance with international standards and current Russian norms.
- ▸Completed to premium quality, within original budget and ahead of schedule; The employer's full satisfaction was achieved.
- ▸It was the first capacity increase at Yajva Power Plant since 1965.
- ▸Siemens F-class gas turbine was put into operation for the first time in Russia with this project and achieved one of the best operating performances in the country.